In October 2026, Starway Roof Systems replaced an aging, leaking roof and the gutters on a home in Williamsport, Pennsylvania. Under the old shingles, two sections of the roof had water-damaged decking, so we replaced that decking, added insulation baffles and a better ridge vent, and installed Owens Corning TruDefinition Duration Designer shingles in Black Sable with new 6-inch seamless gutters. The job took two days.

The back of the Williamsport home with its old brown shingle roof before the replacement

Before: the back of the home with the old shingle roof.

Project Snapshot

  • Location: Williamsport, PA
  • Completed: October 2026
  • Old roof: Asphalt shingles near the end of their life and starting to leak
  • New roof: Owens Corning TruDefinition Duration Designer shingles in Black Sable
  • Decking: Replaced on two roof sections
  • Ventilation: New insulation baffles on those sections and a non-rolled ridge vent in place of the old rolled vent
  • Plumbing vent: Old pipe boot replaced with an all-metal Master Flow pipe collar
  • Gutters: New 6-inch seamless aluminum gutters with 3x4 downspouts
  • Time on site: Two days
  • Cost: About $30,000 for the roof and about $4,000 for the gutters

The Problem: An Aging Roof That Had Started to Leak

The homeowners called us because the roof was getting up in age and had started to leak. When we inspected it in August 2026, we found:

  • Worn shingles across the roof.
  • Nail pops: nails that had worked their way up and pushed through the shingles above them, opening a path for water.
  • A worn pipe boot around the plumbing vent, one of the most common places for a roof to leak.
  • Water-damaged decking on two sections of the roof.
  • An older rolled ridge vent.

Inspection photo of a nail pushing up through an asphalt shingle, circled in yellow

From our inspection: a nail pushing up through a shingle.

Inspection photo of the old pipe boot around a plumbing vent, with a note that it will be replaced with an all-metal Master Flow pipe collar

From our inspection: the old pipe boot, marked for replacement.

Our inspection report marked each of these on photos, so the homeowners could see what we found and what the proposal covered before any work started. For more on what we look at, see what to expect from your roof inspection.

What We Did

Protected the Yard and House

Tarps spread over the landscaping and around the house during the shingle tear-off

During: tarps over the landscaping and around the house during the tear-off.

Before the tear-off, we spread tarps over the landscaping and around the house, and covered the air conditioning unit, to catch old shingles and nails.

Tore Off the Old Roof and Replaced the Damaged Decking

Sheets of water-damaged roof decking removed from the Williamsport roof

During: water-damaged decking removed from the roof.

We removed the old shingles down to the decking. On the two sections we had flagged at the inspection, the decking was stained and coming apart, so we replaced it with new sheathing. A new roof is only as solid as what it's nailed to.

New roof decking being installed over the rafters on one section of the Williamsport roof

During: new decking going on over the rafters.

Improved the Ventilation

On the two sections we redecked, we added insulation baffles. Baffles hold the insulation back from the eaves so outside air can flow in under the roof and up to the ridge. We also replaced the old rolled ridge vent with a more efficient non-rolled ridge vent. Good airflow keeps the attic drier and helps the new shingles last. Read more about ridge vents and roof ventilation mistakes.

Installed the New Roof

Ice and water shield went on the first 6 feet up from the roof edge, around every roof penetration and along the sidewalls. The new shingles are Owens Corning TruDefinition Duration Designer in Black Sable. At the plumbing vent, we replaced the old pipe boot with an all-metal Master Flow pipe collar, so there's no rubber gasket to dry out and crack. See why ice and water shield matters.

The back of the Williamsport home with the new Black Sable shingle roof near the end of the install

The back of the home with the new Black Sable roof near the end of the install.

Replaced the Gutters

The old gutters came off, and new 6-inch seamless aluminum gutters went on, made on site with our gutter machine. The homeowners upgraded to larger 3x4 downspouts, which carry more water and are less likely to clog than standard 2x3 downspouts. See seamless gutters and gutter sizes.

The garage of the Williamsport home after the roof and gutter replacement, with the new dark roof and gutters

After: the garage with the new roof and gutters.

How Long It Took

We inspected the roof in August 2026. The roof and gutters were installed in October 2026 and took two days on site, including the new decking.

What It Cost

The roof replacement, including the decking, baffles, ridge vent and pipe collar, came to about $30,000. The new gutters and downspouts were about $4,000. Every roof is priced on its own size, pitch and condition. See our roof replacement cost guide for current ranges.

The Result

The home has a new Owens Corning roof over solid decking, better attic ventilation, a plumbing vent that won't rely on a rubber boot, and new 6-inch gutters with larger downspouts. The leak is fixed at its source, and the roof is set up for the decades ahead.

FAQs About This Project

Why did this roof need new decking?

Two sections of the roof had water-damaged decking that was stained and coming apart. Decking is replaced when it is damaged, because new shingles need a solid surface to nail into.

What is a nail pop?

A nail pop is a roofing nail that has worked its way up and pushed through the shingle above it. It opens a small hole for water and is a common source of leaks on older roofs.

Why use a metal pipe collar instead of a rubber pipe boot?

Rubber pipe boots dry out and crack over time, which is one of the most common causes of roof leaks. An all-metal Master Flow pipe collar has no rubber gasket to fail.

Why upgrade to 3x4 downspouts?

Larger 3x4 downspouts carry more water than standard 2x3 downspouts and are less likely to clog, which helps 6-inch gutters drain in heavy rain.

How long did this roof and gutter replacement take?

Two days on site, including replacing the decking on two roof sections.

How much did this roof replacement cost?

About $30,000 for the roof and about $4,000 for the gutters. Every roof is priced on its own size, pitch and condition.

Does Starway Roof Systems work in Williamsport?

Yes. Starway replaces and repairs roofs in Williamsport, South Williamsport, Montoursville and Jersey Shore.

Planning a Roof Replacement in Williamsport?

If your roof is aging or starting to leak, we can take a look and walk you through your options. See our roofing services in Williamsport, or read about ice dams in Williamsport and replacing the roof on an older Williamsport home. Schedule a free roof inspection, contact us, or call (814) 308-0490.

Call Starway Roof Systems: (814) 308-0490

Replacing the Roof on an Older Williamsport Home: What to Expect

1 min read

Replacing the Roof on an Older Williamsport Home: What to Expect

About half of the homes in Williamsport were built before 1940. Replacing the roof on one of them is a little different from a newer house: the roofs...

Read More
When to Replace Gutters: Signs, Timing and Cost

1 min read

When to Replace Gutters: Signs, Timing and Cost

The best time to replace your gutters is when you replace your roof. If you can do both together, we recommend it. Otherwise, any season works:...

Read More
Top 5 Signs Your Roof Needs Repairs in Central PA

1 min read

Top 5 Signs Your Roof Needs Repairs in Central PA

The clearest signs your roof needs repair are stains on your ceilings, a lot of shingle granules in your gutters, fiberglass showing through the...

Read More